• Skip to primary navigation
  • Skip to main content
  • Skip to footer
Crossland logo.

Crossland

Real Builders

  • Companies
        • Recent News
        • Federal Bureau of Prisons Leavenworth

          Attracting Talent in 2026: Why Crossland Is the Place to Build Your Career

          Crossland Recognized in ABC’s 2026 Top Performer Rankings

        • Crossland Construction
          • Crossland Construction
            • Columbus, KS (HQ)
            • — Midwest Division
            • — National Accounts
            • — Civil Division Services
            • Rogers, AR
            • Denver, CO
          • Crossland Construction
            • Wichita, KS
            • Kansas City, MO
            • Springfield, MO
            • Oklahoma City, OK
            • Tulsa, OK
            • Prosper/Fort Worth, TX
        • Our Companies
          • Crossland Construction
          • Crossland Heavy
          • Crossland Prefab
          • Crossland Realty a division of Crossland Construction Co., Inc.
  • Projects
    • Construction
    • Heavy Contractors
  • About
    • Our Story
    • Leadership
    • Services
    • Crossland Cares
    • Safety
    • In-House Craftsmanship
    • In-House Training
  • Resources
  • News
  • Careers
    • All Careers
    • Early Careers
    • Skilled Craft
    • Professionals
    • Internships
    • Apprenticeship
    • High School
    • Veteran’s Support
  • Contact Us
    • Office Locations
    • Subcontractors
  • Search

Washburn University Recital Hall

View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.
View larger photo.

Washburn University Recital Hall: Fast-Track Construction Creates Premier Performance Venue in Kansas


Topeka, KS

The new Washburn University Recital Hall stands as a testament to what’s possible when construction teams embrace flexibility and collaboration. This 9,200 SF performance venue, completed through a design-bid-build approach, showcases how thoughtful planning and adaptive project management can turn scheduling challenges into triumphant outcomes.

What began as a standard construction timeline transformed into an impressive feat of acceleration when Washburn University approached the team in February 2025 with an ambitious request: complete the $6.7 million project three and a half months ahead of the original August deadline to accommodate their annual donor event and ribbon cutting ceremony.

The recital hall’s integration with existing campus infrastructure presented unique logistical complexities that required careful sequencing and site management. Working within the constraints of an active university campus, the construction team developed strategies to minimize disruption to daily academic activities while maintaining project momentum. This delicate balance between construction productivity and campus life became one of the project’s defining characteristics.

The accelerated timeline demanded exceptional coordination between all project stakeholders. Construction crews, design professionals, and subcontractors aligned their efforts to compress the schedule without compromising quality standards. This collaborative approach proved essential as the team navigated the intricacies of connecting new construction to existing building systems while working within a confined job site.

The completed recital hall now serves as a premier performance space for Washburn University’s music and arts programs. Its seamless integration with the existing campus architecture creates a cohesive addition that enhances both the physical and cultural landscape of the university. The project’s success extends beyond its physical completion to include the strategic timing that allowed the university to showcase this new facility during a crucial fundraising event.

Project Facts

Industry Sector: Educational
Cost: $6,637,000
Size: 9,200 SF
Delivery Method: Design-Bid-Build / Hard Bid
Owner: Washburn University
Architect: SDG Architecture+Interiors
Engineer: Latimer, Sommers & Associates P.A.

READY TO GET STARTED? READY TO GET STARTED? READY TO GET STARTED? READY TO GET STARTED? READY TO GET STARTED?

Let’s Build

Ready to lay the groundwork?

Contact Us

Find a Career

We’ve got a hard hat with your name on it.

Latest News

Looking for More?


2 min read
Federal Bureau of Prisons Leavenworth
Read More→
2 min read
Attracting Talent in 2026: Why Crossland Is the Place to Build Your Career
Read More→
2 min read
Crossland Recognized in ABC’s 2026 Top Performer Rankings
Read More→

Footer

  • Contact Us
  • News
  • Careers
  • About
  • Projects
  • Companies
  • Services
  • Crossland Construction
    • Columbus, KS (HQ)
    • — Midwest Division
    • — National Accounts
    • — Civil Division Services
    • Rogers, AR
    • Denver, CO
  • Crossland Construction
    • Wichita, KS
    • Kansas City, MO
    • Springfield, MO
    • Oklahoma City, OK
    • Tulsa, OK
    • Prosper/Fort Worth, TX
  • Crossland Heavy
    • Columbus, KS (HQ)
    • Kansas City, MO
    • Omaha, NE
    • Rogers, AR
    • Tulsa, OK
    • Prosper, TX
    • Oklahoma City, OK
Crossland logo.
Subcontractors Employee Login

Connect With Us

Find us on Facebook Find us on Twitter Find us on YouTube Find us on Instagram Find us on LinkedIn
© 2026 Crossland Construction Company Inc. | Privacy Policy
Aetna Transparency In Coverage