Gene George Boulevard Improvements
Successful street improvements project
Springdale, AR
Crossland Heavy Contractors completed street improvements to approximately 1,955 LF of four-lane Gene George Blvd., including a 200′ structural steel bridge over Brush Creek and 2,000 LF of 24″ ductile iron water main utility construction.
CHC did a great job tracking all work activity production and managing the project budget for equipment and overhead. The earthwork, storm activities, and water main work came under budget, achieved by operating with smaller crews and smartly managed equipment rental. The quality of the product constructed by our team was noted and appreciated by the City of Springdale and Springdale Water Utilities. It was a successful project for CHC. The owner, engineer, and all entities were delighted with the outcome.
Project Facts
Industry Sector: Transportation
Cost: $5,100,000
Delivery Method: Design-Bid-Build / Hard Bid
Self-Perform: Below-Grade Utilities, Deep Foundation, Structural Steel
Owner: City of Springdale
Engineer: Engineering Services, Inc.
Let’s Build
Ready to lay the groundwork?
Find a Career
We’ve got a hard hat with your name on it.