This project for Tulsa Community College (TCC) comprised of two additions to an existing building as well as three floors of renovations of a second building, covering a total of 25,000 square feet. The new additions included a building façade and tower, and a large lobby area and coffee shop constructed using a lot of glass. The three floors of renovations include office suites, conference rooms, large open areas, bathrooms, a student orientation area, a testing center, a new boardroom, and a provost office.
Pre-Construction was the most critical time for Crossland to ensure that we could successfully deliver this project. We came on board after the schematics and shop drawings had been done and a lot of the Pre-Construction phase was complete. This meant we actually started with the project over budget so we went straight into value engineering to bring the project back under budget, working closely with the owner and architect.